Sort | Existing method | Trust method |
---|---|---|
Execution method | Association as the implementer + Construction company contracted for construction | Executed by the trust company (agency) (Project operation is coordinated with the association or urban renewal project management committee) |
Concept | Construction company provides funding, and is responsible for construction | Direct execution (agency) by trust company through land trust, funding, project cost execution |
Remarks | Can present confirmed share for association members Construction company's project leadership Possibility of construction cost increase and construction delay (suspension) |
Easier project cost funding and securing of project transparency Cost reduction effect such as reduced construction unit price Must complete construction regardless of sales market conditions |
Since March 2016, the requirements for designated developers (sole implementers) have been relaxed, expanding opportunities for trust companies to execute urban renewal projects as designated developers.
If a certain percentage of land and property owners wish to designate a trust company as the project implementer, the mayor or county governor can designate the trust company as the designated developer (sole implementer).
※ Essential requirements for a trust company to be designated as a developer (sole implementer)
Since July 2016, the requirements for trust companies to become project agents have been relaxed. If a certain percentage of land and property owners wish to designate a trust company as the project agent, the mayor or county governor can designate the trust company as the project agent.
※ Essential requirements for a trust company to become a project agent